Natural stone patio

INSTALLATION STEPS

STEP 1 :
Mark the area to be redeveloped with an aerosol paint. Please provide 6 inches more on each side to provide better accessibility and space for curbs.

STEP 2 :
Excavate 9 inches deep in sandy soil, and 12 inches in clay soil. Plan a slope of 2% to circulate the surface water.

STEP 3 :
Install a geotextile membrane that will prevent contamination of 0-3/4" crushed stone with existing soil.

STEP 4 :
Place the wooden stakes inside the surface every 10 feet. Stretch a rope at the same level where the stones will be laid.

STEP 5 :
Fill with 3 inches of crushed stone 0-3/4", water lightly and compact with the vibrating plate in one direction and then in the other, repeat this process until you have got a foundation 6 inches deep in sandy soil and 9 inches in clay soil.

STEP 6 :
Install the two metal pipes at a distance of 6 feet at the same level as the stone dust bed. Spread 1 inch of stone dust. Slide the wooden board on the pipes of metal and move the pipes as you go. Remove the excess stone dust.

STEP 7 :
Place the natural stones making sure that the level matches. If necessary, remove or add stone dust. Be sure to keep the same distance between each stone if possible. If necessary, cut the stones with a cold chisel or guillotine. Remember to wear safety glasses.

STEP 8 :
Install pavers and push 10" nails every 2 feet.